Case Studies

The Challenge

Viterra operates in North America, Australia, New Zealand, and China. The company, based in Regina, Saskatchewan, is structured into three business units, including an agri-products division that manufactures and sells fertiliser.

Storing bulk fertiliser is not straightforward. If left unchecked, its weight can push out the sides of the large tin sheds typically used to store agricultural nutrients. To prevent this, fertiliser suppliers construct robust internal retaining walls to absorb the pressure around the building's edges and to separate different types of fertiliser.

Agri-business giant Viterra had already installed retaining walls at its fertiliser stores in Geelong and Adelaide but encountered health and safety issues with conventional building techniques. An additional complication was that the landlord of its 150 by 70 metre Geelong store insisted Viterra could only use removable materials to construct retaining walls, without causing permanent damage to the building's concrete slab floor.

The Solution

Rohan Pollard of Blueprint Consulting Engineers explained that Viterra was exploring several options and required an engineer-designed system with removable walls. "Interbloc provided exactly what Viterra needed at a price they were comfortable with. The solution exceeded Viterra's requirements in every way," Pollard stated.

Health and safety were of utmost importance. "The Interbloc approach doubled the safety factor at the stores, which was crucial for Viterra. As a large company, Viterra needed assurance in its health and safety systems. The company wanted a solution compliant with the code, as its existing walls were under strength and under capacity," Pollard emphasised.

In total, there are now 1.2 kilometres of Interbloc walls across the two sites. This involved shipping approximately 3,000 tonnes of blocks from New Zealand, along with 45 tonnes of reinforcing steel, and pouring 1,700 cubic metres of concrete.

The Benefits

Pollard stated that the beauty of the Interbloc approach lies in its flexibility, allowing Viterra to decommission an entire wall and re-erect it in another location: "It's simply a matter of unbolting and moving. Relocating a wall might take a couple of days." This level of flexibility and speed was crucial to the overall project. Viterra required the work to be completed with minimal disruption. Pollard mentioned that the company could not afford to shut down its facilities for six months to accommodate building work: "Interbloc managed to operate with minimal disruption to the existing sites."

Products used in this project

1200 Standard Block

Interbloc

Modular Wall Systems
Explore

Standard Fixing Kit

Our fixing kits come with nuts, washers, bars, couplers and Epoxy
Enquire

Envirobuild

Build your designs with our software
Explore